DOTr reports major right-of-way gains for subway, rail projects

As of December 2025, the DOTr has acquired 90.76 percent of right-of-way and properties needed for the Metro Manila Subway Project. For the NSCR north segment, the agency said at least 56 percent of land has already been cleared and made buildable, a sharp improvement from early 2025 levels.
5 Oct 2024
1:04PM

Metro Manila subway on track for 2028 partial operations

The Metro Manila Subway is expected to start partial operations by 2028, initially connecting Valenzuela City to North Avenue, Quezon City.
22 May 2024
9:44AM

Philippine subway targets 2029 completion

The Metro Manila Subway aims for full operation by late 2029, with the current construction progress of 14 percent.